WestScott Construction demoed the interior stalls, all the plumbing fixtures, and the floor tile at the construction site.
Troughs were then cut in the floor to install four floor drains; two in each restroom. There were also troughs cut to install floor mounted toilets.
All the plumbing pipes were replaced, new electric hand dryers installed, and new lighting fixtures were added. WestScott installed all new stalls, dividers, and doors. The stalls are framed in for two closed in closets. There was also a new drinking and bottle filling station installed right outside the newly renovated restrooms. The concrete flooring was refinished to complete this project.